ladder/school/st_timing_utils.st · 1523 字节 · 下载原文
(* TimingUtils — Helper functions for traffic timing calculations *)
(* Calculate the total cycle time from an array of phase durations *)
FUNCTION CalculateCycleTime : TIME
VAR_INPUT
durations : ARRAY[*] OF TIME;
END_VAR
VAR
i : DINT;
total : TIME := T#0s;
END_VAR
FOR i := LOWER_BOUND(durations, 1) TO UPPER_BOUND(durations, 1) DO
total := total + durations[i];
END_FOR;
CalculateCycleTime := total;
END_FUNCTION
(* Find the longest phase duration in an array *)
FUNCTION FindLongestPhase : TIME
VAR_INPUT
durations : ARRAY[*] OF TIME;
END_VAR
VAR
i : DINT;
longest : TIME := T#0s;
END_VAR
FOR i := LOWER_BOUND(durations, 1) TO UPPER_BOUND(durations, 1) DO
IF durations[i] > longest THEN
longest := durations[i];
END_IF;
END_FOR;
FindLongestPhase := longest;
END_FUNCTION
(* Validate that all phase durations meet a minimum threshold *)
FUNCTION ValidateMinDurations : BOOL
VAR_INPUT
durations : ARRAY[*] OF TIME;
minAllowed : TIME;
END_VAR
VAR
i : DINT;
END_VAR
ValidateMinDurations := TRUE;
FOR i := LOWER_BOUND(durations, 1) TO UPPER_BOUND(durations, 1) DO
IF durations[i] < minAllowed THEN
ValidateMinDurations := FALSE;
RETURN;
END_IF;
END_FOR;
END_FUNCTION
(* Scale all durations by a percentage factor (100 = no change) *)
FUNCTION ScaleDuration : TIME
VAR_INPUT
duration : TIME;
percent : INT;
END_VAR
ScaleDuration := duration * percent / 100;
END_FUNCTION